Are there currently any projects similar to this one in San Diego?
Yes, a battery storage project has been operating in Escondido since 2017, and a battery storage project in Otay Mesa began operating in 2020.
Yes, a battery storage project has been operating in Escondido since 2017, and a battery storage project in Otay Mesa began operating in 2020.
Yes, the project team is committed to hiring locally and using union jobs as applicable.
Construction is expected to begin in 2023 and last for approximately eight to 10 months to meet a 2024 operations date, subject to all applicable approvals.
The project team will work with the community to ensure the facility fits in as seamlessly as possible. Potential ideas include trees and a community mural.
Periodic on-site security checks will be conducted in addition to the remotely controlled security operations.